Western Isles Map Link to Statistics Pages Link to Eriskay Pages
What's New?

Link to Gaidhlig Pages

30 June 2001

The emphasis of work in the week up to June 30 was strongly environmental with work continuing to reinstate land affected by the Uist quarry and the haul road as well as around other parts of the project area. As the project moves towards completion, the number of people employed on it is starting to fall, dropping below 50 for the first time since last August. Work also continued on the completion of the roadways.

Causeway - North and South

The summary of causeway work included:

Causeway - Uist Quarry:

  • Reinstatement continuing

Road and Services:

Glendale Junction

  • Main road complete with wearing course - junctions and passing places remain
  • Signpost installation begun
  • Causeway cattle grids completed
  • Services installation 95 per cent complete
  • Reinstatement works continuing

Weather:

  • Fine at start of week; heavy showers latter part of week

Personnel:

Workforce at the Gap just before closure

  • 48 total employed on site (including 2 CnES) - 56 per cent resident in the Western Isles

Completion programme:

  • Causeway construction - including road, white lines & signs - before mid July
  • Ceann a Gharaidh construction - before mid July
  • Reinstatement works, including quarry - before mid July
  • Local opening planned for 12th July