1 September 2001Minor works continue at Ceann a Gharaidh :- Traffic signs have been erected CnES
are placing navigation buoys for the new ferry route Week
ending 25th started misty becoming stormy (Tuesday) fairing up again
occasional showers. Week ending 1st September started fair becoming very wet on the Tuesday, fairing up again, becoming changeable. |
29 September 2001Progress between the 16th September and 29th September included: Surfacing of sundry works has been completed and the existing road between the South Glendale junction and the quarry haul road has been overlaid.
|
14 July 2001 - Ceann a GharaidhAs of July 14, the Ceann a Gharaidh and quarry reinstatement were regarded as substantially complete with minor finishing works and completion of demobilisation remaining. |
6 August 2001Work on the Ceann a Gharaidh terminal in the week up until August 6 included: Ceann
a Gharaidh navigation light installed Continuation
of remaining minor works |