Skip Navigation
We are currently testing a new website »» Preview Our New Site ««

Harbour Master

Notices to Mariners

HARBOUR WORKS AT STORNOWAY FERRY TERMINAL 

All vessel Skippers/Owners are advised that extensive marine works will commence at Stornoway Pier 3 from 7th April 2014 until October 17th 2014

Works will involve reclamation of ground to the east of the current ferry marshalling area, and piling and decking from the end of the existing pier to the dolphin roundhead. Marine plant in use will include a 35m barge and an 11m workboat/tender.

Ferry services currently operating from Pier 3 will be relocated to Pier 1 from 4th May 2014 until the first week of September 2014.

The light Q(2)G.10s  on the end of pier 3 will soon need to be extinguished due to the pier  extension works. It is currently expected to extinguished between 14th April 2014 and 25th August 2014.

For further information please the harbour office. 01851702688