Developments
Perceval Road Development
Progress is as programmed with a completion scheduled for Feb 2009. Progress on site sees all timber frames to blocks erected and roofing works nearing completion. First fix joinery and plumber work is underway throughout the units. The main site infrastructure connections including electrical and gas are due to complete shortly and external works including drainage and road works are at an earlier stage.
Gleann Dubh
Calmax Construction Ltd have just completed work on part of phase 2 of these semi-detached properties. These houses will be allocated in March 2008.


Gearraidh Ghuirm
An extra 2 houses in this scheme have just been completed by Alex Murray Construction. The 2 bedroom semi's are to be allocated w/c 12/11/07.
.jpg)
.jpg)
Muirneag Court
Work has just been completed by UBC finishing off these flats situated in Stornoway town centre. The flats will be allocated in early November.

Eitseal
Alex Murray Construction Ltd have just completed work on these properties. These houses were allocated in July 2007.


Milestone Cottages
Calmax Construction Ltd have just completed work on these 2 bedroom semi-detached properties. These houses will be allocated by June 2007.