| Application Process for Large Scale Wind Farms
Considerations of what will be involved with processing applications
for >50MW windfarms in the Western Isles.
5 October 2004.
ELECTRICITY ACT 1989
Applications for Consent
Introduction
Developers of power stations (which include renewable energy
developments) with an installed capacity in excess of 50 MW are
required to obtain consent from the Scottish Ministers under Section
36 of the Electricity Act 1989. Such consents usually also deem
planning permission.
This means that application for consent must be made to the Scottish
Executive and not to the Planning Authority.
Environmental Statement
The developer is required to undertake an assessment of the potential
environmental impacts of the proposal. These have to be set out
in an Environmental Statement. The Environmental Statement should
therefore contain a detailed description of the project, along
with a detailed examination of the potential environmental impacts
and the measures to avoid, mitigate or compensate for these impacts.
It should include all stages of the project: construction, operation
and if appropriate, de-commissioning.
The developer is also required to place notices in local and
national press advertising the fact that application for consent
has been made. These notices must be placed in a national newspaper
for one week and in at least one local newspaper for two consecutive
weeks and should provide:
- A brief description of the project and its location;
- Advice on where the Environmental Statement can be viewed;
- Advice on where a Non-technical Summary of the Environmental
Statement can be obtained and where a copy of the Environmental
Statement itself can be purchased (at reasonable cost); and
- Advice on how, by when and to whom representations should
be made.
Consultation Process
The Scottish Executive is required to consult a number of bodies
for their views on whether the proposal is acceptable; what changes
might be needed and so on.
These organisations include:
- The relevant Planning Authority (in the case of the Western
Isles this is the Comhairle).
- Scottish Natural Heritage.
- SEPA.
- Historic Scotland.
In addition, a wide range of Government Departments (such as
DTI, and the Ministry of Defence) statutory bodies (such as Scottish
Water, National Air Traffic Services, Highlands and Islands Airports,
Salmon Fishery Boards, telecommunications organisations, and so
on); as well as others, such as RSPB, are consulted.
Responses to Consultation
The relevant planning authority has 4 months in which to respond.
All other organisations are required to respond within 28 days.
Public Consultation
Members of the public are invited to make representations to
the Scottish Executive. These can be copied to the Comhairle,
or separate representations can be made to the Comhairle.
These must be in writing. That means a letter or an e-mail containing
a verifiable address. Mobile phone text messages are not acceptable.
These should be made within a 28-day period starting from the
second notice in the local press. Representations made beyond
then will not be disregarded provided they are made before the
end of the period for the relevant planning authority to respond
(that is 4 months).
Representations made beyond the 4-month period will not be considered.
However, should the matter go to Public Inquiry it will be for
the Reporter(s) to decide whether late representations will be
heard.
The Role of the Comhairle
The Comhairle has a key role in the process since, if it objects
to the proposal and does not withdraw that objection, the matter
must be referred to a public inquiry (PLI).
If the Comhairle does not object, or its objection can be met
by changes to the proposal, or by conditions that overcome its
objection, then a PLI is not required.
How Will a Decision be Made?
Ministers are required to take into account all the relevant
considerations in reaching a decision.
In general this means that Ministers must take account of the
impacts on people; the environmental impacts; and impacts on the
built and cultural heritage. Noise, construction traffic movements,
television reception, aviation and visual impacts would all be
important considerations under this heading.
Ministers must pay particular attention to international and
national designations, ranging from Natura sites, SSSIs, National
Scenic Areas and their obligations in respect of protected species.
Overall, Ministers must have regard to planning considerations;
the wider policy objectives, whether in respect of energy, environmental
or other policies; and the representations received.
Public Inquiries
Ministers are required to refer the matter to a PLI if:
- The relevant planning authority makes an objection that is
not subsequently withdrawn
- If there are unresolved matters, which, in the Minister’s
opinion, can only be resolved by means of a public inquiry
- If there has not been an appropriate means for people to
make their views known.
THIS MEANS THAT A DECISION ON A PUBLIC INQUIRY, EXCEPT
WHERE THE PLANNING AUTHORITY HAS OBJECTED, IS FOR THE MINISTER
TO MAKE.
Timing
It is unusual for a decision to be made in much less than 12
months.
It is much more usual for it to take longer. How much longer
depends on the complexity of the issues and in some cases the
need for further information to be provided by the applicant.
|