Skip Navigation
Follow us on twitter...

Department of Technical Services

Sound Of Barra Integrated Transport Project

Ard Mhòr Ferry Terminal Construction

14 February 2002

Work progressing on Marshalling Area

Work progressing on Marshalling Area

Work on the new terminal and access road was nearing completion by February 9 at Aird Mhor.

The roadwork earthworks was complete as was the Timber Alignment / Berthing Structure. The installation of diagonal timber bracing and steel walkway had started while beside the roadway the reinstatement and landscaping of the rock source continued. Overall work on landscaping continued beside the road.

The personnel employed amounted to 24 in total of whom 9 are resident in the Western Isles.

Weather: Wet and windy, gale force a lot of the time.

 

Page Last Modified : 29/09/2011 14:06:24