Skip Navigation
Follow us on twitter...

Department of Technical Services

Sound Of Barra Integrated Transport Project

Ard Mhòr Ferry Terminal Construction

15 October 2001

Pumping out

Pumping out

Blasting and drilling continued in the construction work for the access road to the new ferry terminal in the first fortnight of October despite high winds and rain.

Progress between 1st and 11th October saw:

Work in progress on slipway toe walls

Work in progress on slipway toe walls

The breakwater at low level is 65 per cent complete by volume.

Slipway concreting started October 5 and two out of three toe pours have been cast as well as two out of nine berthing walls.

There are three tracked excavators and two articulated dump trucks on site.

Personnel: 21 total, of which 10 are resident in the Western Isles.

Weather: strong winds and showers.

 

Page Last Modified : 29/09/2011 14:06:24