Sound Of Barra Integrated Transport Project

Ard Mhòr Ferry Terminal Construction

Date Update
23/02/02 Final surfacing work underway
14/02/02 Completion of roadwork earthworks
30/01/02 Latest photographs
29/01/02 Work on Timber Alignment / Berthing Structure
19/01/02 Work on roadbed and associated services
12/01/02 Arrival of mobile concrete pump and a 35-tonne crawler crane
22/12/01 Breakwater core and armouring completed
08/12/01 Slipway concreting completed
24/11/01 Breakwater nearly 85 per cent complete by volume
10/11/01 Access road close to completion
27/10/01 Breakwater to be extended
15/10/01 Slipway concreting started
29/09/01 Cofferdam has been constructed
18/09/01 Work on Approach Road and Breakwater
11/09/01 Work on Access Road
21/08/01 Full-scale work begins

 