Sound Of Barra Integrated Transport Project

Ceann a Gharaidh Ferry Terminal Construction

24 February 2001

View of Marshalling Area

View of Marshalling Area

Marshalling Area: blasting completed - rock extraction continuing - over 90 per cent complete
Breakwater: rock armouring in progress - 70 per cent complete
Slipway: fill, armour and preparation for concrete works
Access Road: blasting completed; road filling continued

17 February 2001
Marshalling Area: blasting completed - rock extraction continuing - over 90 per cent complete
Breakwater: rock armouring in progress - 70 per cent complete
Slipway: fill, armour and preparation for concrete works
Access Road: blasting completed; road filling continued

View of Breakwater

View of Breakwater

10 February 2001
Marshalling Area: rock extraction continuing - over 90 per cent complete
Breakwater: rock armouring in progress - over 60 per cent complete
Access Road: filling in progress along shore

3 February 2001
Marshalling Area: blasting and excavating in progress - 90 per cent complete
Breakwater: rock armouring in progress - 60 per cent complete
Access Road: filling in progress along shore

 