Sound Of Barra Integrated Transport Project

Ceann a Gharaidh Ferry Terminal Construction

25 November 2000

View of Ceann a Gharaidh

View of Ceann a Gharaidh

Marshalling Area: blasting and excavating in progress - over 50% complete.
Breakwater: core filling 130m into the sea at low level and rock armouring was in progress.

18 November 2000
Marshalling Area:blasting and excavating was again in progress with the work over 50% complete.
Breakwater: The core filling had pushed 140m into the sea at low level. Rock armouring was in progress.

Ceann a Gharaidh breakwater

Ceann a Gharaidh breakwater"

11 November 2000
Marshalling Area: Work on the ferry terminal at Ceann a Gharaidh was focussed on the marshalling area where blasting and excavating was in progress and is over 50 per cent complete.
Breakwater: the core filling extends 130m into sea at low level and rock armouring is in progress.

4 November 2000
Marshalling Area: Rock blasting and excavation in progress -approximately 50 per cent complete.
Breakwater: core filling 120m into the sea at low level. Rock armouring to core in progress.

 