25 November 2000
View of Ceann a Gharaidh
Marshalling Area: blasting and excavating in progress - over 50% complete.
Breakwater: core filling 130m into the sea at low level and rock armouring was in progress.
18 November 2000
Marshalling Area:blasting and excavating was again in progress with the work over 50% complete.
Breakwater: The core filling had pushed 140m into the sea at low level. Rock armouring was in progress.
Ceann a Gharaidh breakwater"
11 November 2000
Marshalling Area: Work on the ferry terminal at Ceann a Gharaidh was focussed on the marshalling area where blasting and excavating was in progress and is over 50 per cent complete.
Breakwater: the core filling extends 130m into sea at low level and rock armouring is in progress.
4 November 2000
Marshalling Area: Rock blasting and excavation in progress -approximately 50 per cent complete.
Breakwater: core filling 120m into the sea at low level. Rock armouring to core in progress.