2018071627000026
Category
Request Date
Monday, July 16, 2018
Response Date
Friday, July 20, 2018

Question

Section S278 Agreements relating to residential developments during each of the past 5 financial years.
1. Please could you confirm the average time taken from technical submission to the issue of a technical approval? 2. Please could you confirm what is the average time from technical approval to the completion of a Section 278 legal agreement?
 
Section 38 Road Adoptions relating to residential developments during each of the past 5 financial years.
1. Please could you confirm what is the average time taken: a. from technical submission to technical approval to; b. completion of a Section 38 legal agreement to; c. commencement of the maintenance period to; d. the date of formal adoption to; e. notification that any bond can be cancelled?

Answer

I believe the legislation referred to (Highways Act 1980) and the section 278 & 38 agreements specifically referred to only apply in England and Wales.